Wednesday, 14 December 2016
Wednesday, 7 December 2016
Post Production: Editing
We began organising and reviewing footage on the 22/11/16 then began putting a sequence together on the 25/11/16.
By layering the song and adding in the master shots into layers then to cut between them and add transitions and other visuals that suit was the way most efficient for me. I could build the video over the music by getting the main shots and somewhat narrative in.
Rough Cut Deadline: 5/12/16 We presented the Rough Cut to the rest of the class to receive feedback, as a whole they thought it worked visually and that we captured the vie of the music perfectly. The constructive feedback was to add some Effects in eg. on the beat. flashes and so forth.
I took this on board and began colour grading to match and clean up the shots, the main shots were those filmed in the Shisha Bar as this was the look we were going for (Pink/Blue tones) I then created a preset on the shots outside to keep the tone and paste onto the other clips. I altered according to each shot in fine detail.
By layering the song and adding in the master shots into layers then to cut between them and add transitions and other visuals that suit was the way most efficient for me. I could build the video over the music by getting the main shots and somewhat narrative in.
Rough Cut Deadline: 5/12/16 We presented the Rough Cut to the rest of the class to receive feedback, as a whole they thought it worked visually and that we captured the vie of the music perfectly. The constructive feedback was to add some Effects in eg. on the beat. flashes and so forth.
I took this on board and began colour grading to match and clean up the shots, the main shots were those filmed in the Shisha Bar as this was the look we were going for (Pink/Blue tones) I then created a preset on the shots outside to keep the tone and paste onto the other clips. I altered according to each shot in fine detail.
Production: Progress
We shot 2 locations on the first day, the Park and Tate Britain then scheduled in to shoot the Shisha Bar for the friday that week.
The following week we managed to film some shots up on the rooftop, there was a few changes to schedule and call sheet but was amended and planned when we all met so we were all on the same page.
We managed to film enough footage over 3 days. Then processed into the Edit reviewing footage and organising it.
Berfin, Dimi and I took the role of editor at the beginning then I continued with their input and opinions as editing is my strength.
Subscribe to: